Huerfano County expects to begin the Airfield Lighting & Signage Improvements project at the Spanish Peaks Airfield later this month. The Contractor, Electrical Excellence, has provided their anticipated construction schedule for the airport, which contains three (3) total phases over a total of 28 calendar days beginning on Monday May 19th, 2025. In addition to this notice, the County will be posting NOTAMs as directed by the project engineer and contractor. The anticipated project schedule is as follows:
Construction Start: May 19th, 2025
- Phase 3A
- Closure Area: Taxiway A2
- Closure Dates: May 19th to May 22nd
- Phase 2
- Closure Area: Runway 9-27, Runway 2-20, Taxiway A1, & Taxiway A2
- Closure Dates: June 2nd to June 6th
- Phase 3B
- Closure Area: Taxiway A1 & Runway 2-20
- Closure Dates:
- Taxiway A1 – June 9th to June 13th
- Runway 2-20 – June 9th to June 10th
Construction Completion: June 13th, 2025
Any updates to this schedule will be included in the NOTAMs for the project. View the construction safety and phasing plan here: